(974) 4469 0276 / 4469 0639

Perspectives

Construction Progress

Two (2) Schools – Package 1, Stage 7B
Al Shahaniya & Al Shamal
Educational Facilities
Main Contractor
18 March 2012
08 September 2013
Consulting Engineering Group (CEG)
Public Works Authority (ASHGHAL)

Remarks

The project was successfully completed that complied and satisfied all contract and other specified requirements.

Project Description

The schools are namely Al Shahaniya Secondary Girls School and Al Shamal Girls School.  These schools consist of classrooms, art rooms, laboratories, library, teachers rooms, administrative offices, assembly and multi-purpose halls, auditorium, canteen, kitchen, pantries, toilets, changing room, services rooms, ancillary buildings, water tank yard, sports courts, hard and soft landscaping, shaded structures, parking, boundary walls, fence and gates, others including external site services infrastructures.